Turkey Creek Ph 2 - Interceptor


7:45am- gravel is done at MH E31 as crew will level-it up and set the base section next. 

9:41am- MH E31 is now set and rock is getting broke out for first joint of pipe to be laid. 

Line is lamped back to MH E30 also. 

12:03pm- 2 joints now placed upstream of MH E31. 

1:56pm- 5 joints now placed so far. 

3:03pm- joint #6 getting gravel. 

16:02pm- 7th joint in digging for 8th one today. 

MH E30 also being wrapped at this time. 

4:43pm- graveling #8 now. This will wind up the day with backfill to occur. 