Turkey Creek Ph 2 - Interceptor
7:45am- gravel is done at MH E31 as crew will level-it up and set the base section next.
9:41am- MH E31 is now set and rock is getting broke out for first joint of pipe to be laid.
Line is lamped back to MH E30 also.
12:03pm- 2 joints now placed upstream of MH E31.
1:56pm- 5 joints now placed so far.
3:03pm- joint #6 getting gravel.
16:02pm- 7th joint in digging for 8th one today.
MH E30 also being wrapped at this time.
4:43pm- graveling #8 now. This will wind up the day with backfill to occur.