Turkey Creek Ph 2 - Interceptor


Crew to set MH E32 today. 

8:39am- Manhole bases are being unloaded from haul truck first thing this morning…

10:02am- now rebar is being unloaded for encasement that will be built. 

11:02am- crew setting MH E32. 

11:50am- manhole E32 now connected with a 12’ piece of pipe. 

Line is also lamped back to MH E31. 

1:24pm- MH E32 is stacked out and alignment to next manhole is underway. 

2:30pm- rebar is now getting tied for cages. 

3:22pm- two halves almost built. 

4:37pm- 4 halves now built and they will riund out the day on the 5th. 