Turkey Creek Ph 2 - Interceptor


Crew to finish tying cages and should place pipe with bottom cage today. 

9:01am- back to digging now as crew gravels for next run of pipe on encasement at STA 88+50. 

10:25am- 1st joint out of MH E32 placed with bottom section of cage under it. Pipe in background is being used as a water diversion over ditch. 

12:20pm- 3 joints of pipe now in place with cages under them. 

MH’s E30 and E31 getting wrapped and strapped today also. 



1:15pm- top sections of cages going on over pipe now. 

2:30pm- crew will get about 70’ of cage in and then place concrete in the morning. The last 10’ will go in after a wall of rock is broke out for MH E33. 

3:40pm- 5th joint laid today with the last bit of cage getting ready to go in to cover it. 

4:40pm- last top cage is on and backfill will round out the day along with some roadwork. 