7:02am- crew is back at MH E26 to het re-aligned and being laying pipe again this morning. 

8:26am- 2nd joint going in, its a cut piece being 10’ long. 

Wrapping and strapping also occurs at this time at MH E25. Requested larger rocks to be pulled back away from MH. 

10:10am- 5th joint in now. 

11:00am- rock breaking had to occur. Still on 5th joint. 

12:58pm-6 joints in working on the 7th. 

2:30pm- 9th joint placed as wall of rock wall begins dissipating. 

3:30pm- joint 11 goes in. 

4:29pm- 13 joints today so far. Crew will begin wrapping things up for the day due to the heat. 