Turkey Creek Ph 2 - Interceptor


7:53am- Excavator is fetching the manhole from the top this morning. 


9:10am- The manhole is not delivered at this time. There was an issue with Scurlock getting a driver to get it down jere first thing. They now say it will be here around 10:00am.

10:45am- still no manhole...

11:47- MH E26 now onsite as digging now continues. 

1:42pm- grading for MH E26 is now completed. 

2:06pm- base now set and line is lamped back to MH E25 respectively. 



3:03pm- crew now aligned to next manhole, E27 as digging will now resume. 

4:32pm- 1st joint out of MH E26 done laid in place. 

4:45pm- pipe is too close to the wLl as the crew double checks for offset of MH. 

5:12pm- crew pulls joint of pipe to get mew alignment made. This will round out the day today. 









 