Turkey Creek Ph 2 - Interceptor
6:45am- Blasting crew is back to begin blasting in area of MH E1- E6. Flatcreek crew will be bringing equipment from E33 area this way to start laying pipe.
9:43am- more manholes now unloaded.
10:22am- well the Blasting company is taking a different approach to all the creek gravel…
11:15am- Crew is now backfilling behind where the Blasters are working so that they can begin digging to lay pipe.
12:54pm- pipe is now getting moved down line towards E1 location.
2:30pm- Opened E1 manhole to check to see of plug was still in place after close proximity of blasting.
Looks good. Not leaking.
4:15pm- area now backfilled back to E1 fromE3 location.
4:35pm- pipe is getting moved now to roadway from under bridge so that lasting can continue once they get that far.