Turkey Creek Ph 2 - Interceptor
7:05am- crew will continue with pipe laying and slope anchors today.
8:17am- 2nd joint going in for today so far as more rebar is getting set for slope anchors.
9:24am- 3rd joint going in now.
11:11am- another anchor is ready as joint #6 is laid in place as crew nears MH E34 location.
12:56pm- crew has laid 7 joints so far today and tied up and anchored 3 more slope anchors. Crew will now place sheathing on downhill side of anchors to prepare for concrete at 3pm today.
2:21pm- last of the slope anchors are being tied for today. A total of 6 to be poured hy days end.
3:15pm- concrete arrives and is now being placed on slope anchors.
4:30pm- 7 joints of pipe today and 6 slope anchors completed.