Turkey Creek Ph 2 - Interceptor
7:10am- crew will work to get MH E34 set today and do more slope anchors along with two trench seals at MH’s E32-33.
8:00am- 1st joint going for today.
-delay in post due to Phase 1 issue at MH E16. Pictures and video taken and posted on “TEAMS”.
10:43am- 4joints set and MH E34 is tied into line.
Line is also lamped by laser back to MH E33.
12:10am- two joints now placed upstream of MH E34.
Also the last slope anchor is tied up and ready for concrete on the run from yesterday.
1:35pm- 6 joints in place so far today. A 7th will be placed as crew awaits concrete. 1st new slope anchor for today is also being tied for the run above E34.
2:45pm- concrete has finally arrived today. The last slope anchor#9 for 33-34 run has begun.
2:55pm- Finished.
3:05pm- 1st slope anchor above MH E34 now getting concrete.
3:23pm- finished.
3:38pm- trench seal on MH E33 side almost finished.
4:31pm- trench seal on MH E34 side is now completed.
Crew will round out the day with wrapping and strapping of MH E33.