Turkey Creek Ph 2 - Interceptor


7:10am- crew will work to get MH E34 set today and do more slope anchors along with two trench seals at MH’s E32-33. 

8:00am- 1st joint going for today. 


-delay in post due to Phase 1 issue at MH E16. Pictures and video taken and posted on “TEAMS”. 

10:43am- 4joints set and MH E34 is tied into line. 


Line is also lamped by laser back to MH E33. 

12:10am- two joints now placed upstream of MH E34. 
Also the last slope anchor is tied up and ready for concrete on the run from yesterday. 



1:35pm- 6 joints in place so far today. A 7th will be placed as crew awaits concrete. 1st new slope anchor for today is also being tied for the run above E34. 

2:45pm- concrete has finally arrived today. The last slope anchor#9 for 33-34 run has begun. 

2:55pm- Finished. 

3:05pm- 1st slope anchor above MH E34 now getting concrete. 

3:23pm- finished. 

3:38pm- trench seal on MH E33 side almost finished. 

4:31pm- trench seal on MH E34 side is now completed. 

Crew will round out the day with wrapping and strapping of MH E33. 