Turkey Creek Ph 2 - Interceptor


11:00am- crew is at MH E1. Manholes are moved for E2,3,&4. The big Sycamore tree is going to have to come out now. 



11:25am- crew exposing MH E1 stub-out pipe. 

12:56pm- 6” pump now set up in MH E1 with plug on downstream side. 

2:14pm- alignment now done to MH E2 location and 4” pump now pumping. 

Grading for 1st joint of pipe now occurring. 

3:06pm- more water than pumps could handle! Excavator finally made it to the blasted ditch and opened up the 1000’ French drain!!!

3:30pm- getting aligned back up in order to get second joint placed yet today. 

4:43pm- 2nd joint now placed. 

4:55pm- both joints now getting graveled up. 

5:05pm- backfill will round out the day here. 