Turkey Creek Ph 2 - Interceptor
6:49am- crew has a-lot of water in ditch this morning.
Blasting crew has shot across the creek over last Friday and Saturday it appears.
8:42am- still pumping water…
11:05am- 1st joint finally going in!
1:30pm- 3rd joint in place as more dozer work is being done around MH E2.
3:08pm- 4 joint in now as more rock will need broke out.
4:23pm- still on #4. 5th joint for the day should get placed…
4:57pm- both 6” and 4” pumps running and can not keep up with water. Crew will continue to work fighting the water to attempt getting the 5th joint laid for today. I will be headed offsite.