Turkey Creek Ph 2 - Interceptor
Crew will continue to clean pipe today as more rock breaking happens to get MH E33 set and tied in.
7:42am- screen is in place now as crew will attempt to wash rock on into manhole from this section of pipe between MH E32 and what would be 33.
8:54am- working to get cleaned around cage so that they can get a pipe in onto manhole 33 location.
10:32am- a joint is laid to get last 10’ of cage on pipe before setting MH E33 after more rock breaking.
12:05pm- a piece of pipe 7’ long will tie manhole E33 to line right after lunch now.
1:10pm- MH E33 base and riser is mow set in place.
Line is lamped from E32 - E33. As it shows, not all of the rock is removed.
2:42pm- last of the encasement is now finished between E32-E33.
3:22pm- more wrapping and strapping continues today at MH E33.
4:34pm- MH E32 now getting done. This will round out the day with backfill to follow.