Turkey Creek Ph 2 - Interceptor
Crew will work to get a joint or two in above MH E33 and get anchors in stalled on them.
7:52am- top riser is being set on MH E33.
9:13am- a screen is being set up in front of hole to keep rocks from rolling in.
10:31am- 1st joint being placed out of MH E33.
12:39pm- 2nd joint is now placed as crew will begin cutting rebar and building anchors around the joints.
Rest of the anchors will be spaced out every 3rd joint.
2:50pm- 1st slope anchor is set and 2nd is now getting placed with concrete arriving shortly.
3:25pm- concrete now getting placed on slope anchors.
4:00pm- second one is almost done.
4:30pm- the first two anchors are in place. Crew will pick things up and do a little backfill before callingnit a day.