Turkey Creek Ph2 - Interceptor
7:40am- Crew is placing the necessary 20’ of pipe and rebar cages this morning for encasement E03.
-delay in posting due to discussion with about creek crossing and length of encasement, amount of concrete, etc…over-blasting and possible negative affects it would have; increased concrete usage etc…
10:14am- 4th full joint now placed. A 6’ piece was added to the first joint this morning to allow for the encasement.
10:29am- concrete has finally arrived onsite for encasement E03.
10:44am- almost done. A call back for more concrete is needed.
12:00pm- 5th full joint now placed and rest of the encasement is now completed.
1:22pm- 6th joint now getting placed.
2:26pm- trying to get MH E3 area dug out. Banks keep falling off… also having pump hose issues at this time.
2:52pm- MH E3 getting measured out for pipe now.
4:00pm- MH E3 is set and stacked as wrapping begins.
Pipe laid so far today is 101.5’ and E03 encasement.
4:33pm- line is lamped by daylight from E3 back to E2.
Crew will wrap up their day with backfill and such.