Turkey Creek Ph 2 - Interceptor



7:00am Pumping water from ditch to get started for the day.



Excavate and continue to pump water prior to placing first pipe for the day



First pipe in for the day.





Second stick this morning.





Third stick for the day and back filling right behind.







Forth stick of pipe for the day



Placement of the fifth stick of pipe.





Placed # six for the day.



Prepping pad for #7 pipe.



7 sticks of pipe in for the day.



8 sticks of pipe in for the day and continue to back fill along the way







Flat Creek finished the day,  installing 9 pieces of pipe