Turkey Creek Ph 2 - Interceptor
7:08am- crew is back digging to lay more pipe today upstream of MH E5.
8:29am- 1st joint of the day is now in place.
9:37am- 2nd now placed.
11:02am- 3rd full joint plus a 7 footer now installed.
12:42pm- 4th full joint in now.
2:03pm- 6th full joint now getting gravel.
3:15pm- 7th full joint placed.
4:37pm- 8th full joint is in, but rock will need broke now. This will round out their day here.