Turkey Creek Ph 2 - Interceptor


7:30am Bringing in sections of man holes prior to excavation for the day


9:00am Placed first stick of pipe for the day




9:45am Continue to excavate for pipe installation 


10:27am Second stick of pipe in for the day




11:35am Generator start up for lift station 2 all good. Fuel to top off tank will be delivered tomorrow.




11:50am Prepping pad for Mh E6. Travis Tucker will take over for the remainder of the day.