Turkey Creek Ph 2 - Interceptor


7:03am- crews to be back cleaning pipe out from MH E33 downstream today and clearing on Tinker to finish up. MH E6 area has water standing due to pump not running. 

8:59am- more rock coming out of pipe today!

9:49am- clearing is now complete to Carlton Rd. Staking will be done today for rest of blasting from MH E42 on up. 

11:15am- fence building continues back today under the bridge. 

1:15pm- crews are back now at MH E6 to begin digging again to lay pipe. 

2:38pm- some creek work was done first along with more fencing. 



4:21pm- crew setting first joint upstream of MH E6 after alignment took place. This will round out the day with backfill of this first joint. 