Turkey Creek Ph 2 - Interceptor


6:49am- crew will continue digging to cross creek today. 

8:11am- pump is getting moved so that the first joint of the day can be placed. 

9:22am- 2nd joint now placed as crew checks alignment. 

10:04am- water pouring into ditch. 

10:49am- crew has decided to install a liner upstream to make an area to bypass pump the creek. 

11:34am- bypass pumping is now underway. 

12:52pm- crew will call it a day as another 6” pump is needed and wont be available until tomorrow. 