Turkey Creek Ph 2 - Interceptor


6:59am- additional pump is now onsite and will be moved to where existing pump is currently at. 

Wrapping and strapping on E6 will also occur this morning. 

8:41am- both pumps running and reset. Rock breaking occurring now. 

9:57am- rebar bottom half cage going in as pipe is laid. 

11:11am- 2 joints laid now with bottom cages placed. 

1:30pm- 3 joints with cages now placed. 

1:57pm- 4th and final with cages placed as tying of cages together and cross pieces being epoxied into rock occurring. 

2:33pm- concrete is now going on pipe and cages. 

3:08pm- chinking in the concrete. 

3:50pm- double checking to ensure grade of pipe is good. 

5:20pm- 72yds of concrete has been placed and we are not quite half way across the creek. This will end the day. 