Turkey Creek Ph 2 - Interceptor
6:45am- crew started at 6:00am this morning to try and get on across the creek today with the encasement.
8:39am- second joint now placed with bottom half of cage.
9:57am- top cage on now with 3 joints placed. Cross rebar now getting drilled and epoxied in.
10:20am- concrete going in now along with rock breaking beginning again.
11:51am- 3 loads of concrete now placed.
1:36pm- concrete starting to get to flowline of creek. 6 loads now placed.
2:42pm- another section of pipe and cage being prepared and a total of 81 yds of concrete has been placed today on encasement.
4:25pm- 4th joint placed with bottom cage. Trench seal back slope area formed and crew calling it a day since starting at 6:00am this morning. Crew will be starting early rest of the week to help with beating the heat!