Turkey Creek Ph 2 - Interceptor
6:20am- crew to set MH E7 today and finish out concrete encasement.
7:24am- MH E7 base is now set with a 12” piece of pipe tying into line.
Line is lamped by laser back to MH E6.
9:38am- MH E7 mow stacked and alignment to MH E8 is completed. Digging underway now.
10:36am- rest of cage is installed around pipe leading upto MH E7. About 2’ or so of rock is all that will need to be broke out on next run to MH E8.
12:00pm- 1st joint placed upstream of MH E7 as rock breaking continues.
1:08pm- rock broke now for second joint to be dug out and laid.
2:13pm- last of the encasement going in with concrete.
2:56pm- creek channel getting finalized…
3:39pm- 2nd joint is now laid in place.
Water is now diverted back to creek channel.
4:16pm- crew calling it a day since late night yesterday.