Turkey Creek Ph 2 - Interceptor
7:30am Bringing in sections of man holes prior to excavation for the day
9:00am Placed first stick of pipe for the day
9:45am Continue to excavate for pipe installation
10:27am Second stick of pipe in for the day
11:35am Generator start up for lift station 2(6) all good. Fuel to top off tank will be delivered tomorrow.
11:50am Prepping pad for Mh E6. Travis Tucker will take over for the remainder of the day.
12:00pm- LS4 site getting a few wires landed for generator start up here shortly.
12:45pm- started ip generator, transferred power and shut down. More fuel is needed and will be delivered tomorrow Dale indicates.
1:26pm- crew setting MH E6 now with a 11’ piece of pipe to tie it in.
1:50pm- having crew check elevation of flowline from bench mark. We are about 1/2” to 3/4” high…crew will let it ride!
2:32pm- trench is dug back to ensure they are in the blasted ditch line heading across the creek. Excavators are back filling some now to catch back up.
2:53pm- line is lamped by laser back to MH E5.
3:45pm- MH E6 now stacked out as more gravel goes over pipe laid to MH.
4:45pm- temporary fence going up now with top to MH E5 going to be installed. This will round out their day.