Turkey Creek Ph 2 - Interceptor


7:30am Bringing in sections of man holes prior to excavation for the day


9:00am Placed first stick of pipe for the day




9:45am Continue to excavate for pipe installation 


10:27am Second stick of pipe in for the day




11:35am Generator start up for lift station 2(6) all good. Fuel to top off tank will be delivered tomorrow.




11:50am Prepping pad for Mh E6. Travis Tucker will take over for the remainder of the day.


12:00pm- LS4 site getting a few wires landed for generator start up here shortly. 


12:45pm- started ip generator, transferred power and shut down. More fuel is needed and will be delivered tomorrow Dale indicates. 

1:26pm- crew setting MH E6 now with a 11’ piece of pipe to tie it in. 

1:50pm- having crew check elevation of flowline from bench mark. We are about 1/2” to 3/4” high…crew will let it ride!

2:32pm- trench is dug back to ensure they are in the blasted ditch line heading across the creek. Excavators are back filling some now to catch back up. 

2:53pm- line is lamped by laser back to MH E5. 

3:45pm- MH E6 now stacked out as more gravel goes over pipe laid to MH. 

4:45pm- temporary fence going up now with top to MH E5 going to be installed. This will round out their day. 