Turkey Creek Ph 2 - Interceptor


7:00am- crew will begin laying more pipe here today just upstream from MH E4. 

9:22am- 3 joints are now laid so far this morning. 

10:30am- 5 joints now installed. 

Wrapping and strapping also done on E4. 

11:48am- 7 joints installed with #8 waiting. 

#8 getting gravel now. 

1:20pm- grading gravel for #9. 

2:08pm- #10. 

3:55pm- 12 joints now placed. 

4:55pm- working on joint #14 for the day…