Turkey Creek Ph 2 - Interceptor
6:43am- crew will work to get fence moved under bridge and clear area for spoil so pipe laying can continue.
8:12am- clearing is almost done now under the bridge.
Crew also having to work on equipment. Quick connect issues.
10:21am- equipment is temporarily fixed with the second joint of the day about to receive gravel.
A lot of rock will need to be broke out for #3 placement.
12:14pm- 3rd joint almost ready to go in.
1:50pm- 3rd joint now in place, and more rock to be broke.
3:02pm- #4 getting graveled and more rock to be broke out.
4:26pm- 5th joint is placed and digging on 6th to round out the day. Appears they are back into blasted rock now.