Turkey Creek Ph 2 - Interceptor
6:14am- crew is back to digging this morning to lay more pipe again today.
8:15am- no pipe set yet. Water coming into ditch creating issues for laser. Some rock was broke out also.
9:10am- grading gravel to lay first joint of the day. Wrapping and strapping continues on MH E7.
10:06am- breaking rock for second joint.
11:03am- 2nd joint is now placed.
1:16pm- 3rd joint now set n place. A lot of water continues to enter the ditch.
2:10pm- still digging on 4th joint for today and MH E4 gets a 2’ barrel section added and will be wrapped and strapped.
3:13pm- 4th joint now placed with plug going into the end of pipe for the weekend. Crew calling it a day due to the overtime worked on creek crossing.
Backfill occurring to keep pipe from floating.