Turkey Creek Ph 2 - Interceptor


6:59am- pump is getting set back up this morning to begin pumping water from trench. Water is over the pipe. 

8:06am- still pumping water as ditch is getting opened up for laying of the first joint of the day. 

9:10am- joint #1 is now in place. 

10:23am- joint #3 is next up!

11:30am- #4 now in place. 

1:52pm- MH E5 is dug out and manhole base goes in with a 7.5’ piece of pipe to tie it into the line. 

Line is lamped by laser back to MH E4. 

2:50pm- MH E5 is stacked, wrapped and strapped on first section. Alignment ato MH E6 is now underway. 

3:20pm- joint #5 now going in for the day. 

4:25pm- joint 6 awaits gravel. 

5:05pm- 7th and final for the day!