6:52am- crew is already breaking rock again this morning. Should be setting MH E10 before noon today.
7:30am- 1st joint getting placed. Rock breaking will begin at MH E10 now.
8:00am- toured site with Brad and met with contractor and sub for phase 1 fall seeding. Met also with Rittenhouse representative and looked at the fields for remedy’s from of all the weeds growing and no grass.
12:30pm- contractor calls it a day due to the E10 manhole invert being wrong. Crew will resume work tomorrow with a different manhole for the E10 location.