Turkey Creek Ph 2 - Interceptor


Crew will unload manhole at the top and bring it down to MH E10 location. It will be manhole #45 that has con-shield in it. It was the only manhole scurlock had that would work at this location. A new manhole will be made for E45 later on. 

8:31am- a full joint minus the bell is now placed to accept what is now MH E10. 





8:45am- line is lamped by laser back to MH E9. 

9:47am- MH E10 is stacked and alignment to MH E11 location is done. Rock breaking continues. 

11:47am- 2 joints out of E10 now for a sum of 3 total for the day so far. 

1:37pm- 4th joint now placed. 
2:56pm- 5th joint of the day getting placed. 

4:30pm- #6 has landed!

4:57pm- hammer going back on to break rock to round out the day. 