Turkey Creek Ph 2 - Interceptor


6:52am- crew will work to begin crossing the creek today here between MH E11 & E12. 

8:20am- 1st joint out of E11 going in with a check for alignment being done. 

10:03am- 2nd joint going in. 

11:44am- rock breaking a little bit to get across the creek. Encasement will start at end of pipe showing. 

2:09pm- 5 joints total now laid with rebar cages under the last 3 of them as top cages are getting set now. 

2:38pm- drilling for anchors. 

3:40pm- concrete going in. 

4:46pm- 27 yds went down and grading and blocks down for last joint of the day. No more concrete to be put down today. 