Turkey Creek Ph 2 - Interceptor
6:52am- crew will work to begin crossing the creek today here between MH E11 & E12.
8:20am- 1st joint out of E11 going in with a check for alignment being done.
10:03am- 2nd joint going in.
11:44am- rock breaking a little bit to get across the creek. Encasement will start at end of pipe showing.
2:09pm- 5 joints total now laid with rebar cages under the last 3 of them as top cages are getting set now.
2:38pm- drilling for anchors.
3:40pm- concrete going in.
4:46pm- 27 yds went down and grading and blocks down for last joint of the day. No more concrete to be put down today.