Turkey Creek Ph 2 - Interceptor


7:00am- top cage to go on top of last pipe set yesterday. Another 3 full joints +8’ to end of encasement. 

7:46am- breaking rock. 

8:48am- digging out for joint of pipe now. 

9:42am- wrapping and strapping is done on MH E11 now. 

10:41am- 1st joint of the day placed with rebar top cage going on yesterday’s last pipe laid. 

12:15pm- 2nd now in with underlying cage. 
2:04pm- 3rd joint in with cages being placed atop. 

3:04pm- concreting begins. 

3:55pm- 2 loads of concrete now placed. 

4:31pm- more concrete is on its way to finish up encasement on across the creek. This will round out the day. 