Turkey Creek Ph 2 - Interceptor
7:04am- crew will be breaking rock out for MH E12 today and finish placing concrete for reat of encasement.
8:25am- creek channel is getting put back this morning to allow natural water flow again.
11:44am- creek channel is almost done.
MH E12 getting prepped to go into hole.
12:57pm- MH E12 now set and connected to line with one full joint.
Line for is lamped back to MH E11.
1:47pm- MH E12 is checked for grade on inlet side of MH E12 and its 3” low.
2:46pm- backfill up-to manhole 12 is now underway.
3:48pm- 1st joint out of MH E12 now in place.
Gravel also going in.
4:57pm- 2nd joint now in for a total of 3 today. This will round out the day.