Turkey Creek Ph 2 - Interceptor
6:58am- crew will continue with pipe and encasement work here at E-04.
8:07am- crew will now be moving the last two joints placed yesterday due to a rolled gasket.
8:42am- 3rd joint back has to come out. Its where the bad gasket was at.
9:07am- new joint getting installed back now.
10:53am- so, after a long morning the 1st new joint of the day is set.
Dirt work under the bridge is back underway today also.
1:10pm- 4th joint placed for today and final top cages going on pipe for encasement. Concrete to be jere at 3pm.
3:10pm- 6th joint placed for today and still awaiting concrete.
3:45pm- concrete begins.
4:33pm- This will round out the day here. Concreting will continue.