Turkey Creek Ph 2 - Interceptor
7:15am- encasement E-04 will be covered today and more digging to lay pipe on upto MH E10 area leaving a gap so that the upper portion of the line can be “flushed” out.
8:28am- 1st joint of the day now placed.
9:39am- 3rd joint of the day going in.
10:42am- crew has stopped laying pipe for today and will be going back to manholes to finish setting tops and lids today and backfilling.
1:57am- JWX is onsite today spreading seed and straw.
2:20om- crew still installing tops and lids.
4:53pm- crew is moving things back to other end of job now (E33 area) so that work can start back up there. This will round out the day.