Turkey Creek Ph 2 - Interceptor


Crew will be working in MH E34 area today once manholes are unloaded from truck at the quarry then hauled down to line. 

8:11am- preparing to unload and haul manholes down to line area. 

10:26am- back to laying pipe where they had left off at 2 joints above MH E34. 
11:15am- 1st joint of the day now placed. 

1:10pm- 2nd joint now in with 3rd getting graded out and where next slope anchor will be placed. 

2:28pm- 4th joint placed. 

3:56pm- 6 joints placed with 3 open spots for anchors that need to be created yet. 

5:00pm- 7 joints set today. This will round out the day. 