Turkey Creek Ph 2 - Interceptor
Crew will be working in MH E34 area today once manholes are unloaded from truck at the quarry then hauled down to line.
8:11am- preparing to unload and haul manholes down to line area.
10:26am- back to laying pipe where they had left off at 2 joints above MH E34.
11:15am- 1st joint of the day now placed.
1:10pm- 2nd joint now in with 3rd getting graded out and where next slope anchor will be placed.
2:28pm- 4th joint placed.
3:56pm- 6 joints placed with 3 open spots for anchors that need to be created yet.
5:00pm- 7 joints set today. This will round out the day.