Turkey Creek Ph 2 - Interceptor


6:42am- crew has ran into an issue of a gasket that appears to be leaking about 5 joints back from where they are currently at; STA 26+00. 

7:40am- removing pipe. 5 joints to be removed in order to get to rolled gasket. 

9:06am- 5 joints now removed and gasket is pulled from #6. One more joint to now be removed. 



10:08am- re-laying  of  pipe begins as bell and spigots are cleaned. 

11:51am- one more joint to be re-laid to get them back to where the were this morning. 

1:25pm- MH E9 is now getting rock graded out. 

2:17pm- MH E9 base now placed and getting stacked out. 



2:40pm- line is lamped by laser back to MH E8.

3:45pm- alignment to MH E10 is now underway. 

4:27pm- 1st joint out of MH E9 now placed. Grade is at .25% due to pipe being a little high based on hard shot. 

5:15pm- wrapping and strapping will round out the day jere on MH E9. 1full joint and a 9’ pice is all thats laid today that was not redone. 