Turkey Creek Ph 2 - Interceptor


Crew is back to lay pipe again today. They are two joints upstream of MH E9 to begin their day. 

8:21am- 1st joint of the day now placed. 

9:26am- 2nd joint getting gravel. 

10:38am- preparing joint #3 for gravel. 

11:45am- trench seal going in at MH E6 side of creek. 

12:05pm- MH E6 side now completed. 

1:00pm- MH E7 side now underway. 

1:40pm- joint 5 going in now for the day so far. 

3:18pm- #6 now in place. 

4:57pm- hammer is being taken off so crew can dig for setting last joint of the day; #7. 