Turkey Creek Ph 2 - Interceptor
Working on finishing up the install of manhole E8.
Connecting the new sewer pipe.
Backfilling with rock.
Continuing on laying the 27” pipe.
Removing the temporary crossing. Have a new one downstream.
Continuing to dig for new sewer line. Rock and warning tape installed as shown.
Have had to stop a couple times today to break rock to get to depth.
Lowering in another section of pipe. Wrapping up the day.