Turkey Creek Ph 2 - Interceptor


7:17am- crew will work on installing rebar for slope anchors today. Creek hot up with all the rain and washed out roadways. No way to get concrete in today. 

8:50am- 1st slope anchor of the day tied up. 

Two more to go. 

10:26am- 2nd now tied and working on 3rd. 

11:50am- pump is getting set up to fill line for “flushing” today at MH E32. 

1:40pm- 1st joint of the day going in. 

3:18pm- 2nd joint in place working on the 3rd. 

3:43pm- 1st flushing of line is underway at MH E30. Line was filled from E32 down to E30. Plug will be reinstalled and filled again at this location. 

4:55pm- 4th and final joint for today going in. This will round out the day. 