Turkey Creek Ph 2 - Interceptor
7:11am- Crew is back today to lat more pipe and get MH E40 set.
8:33am- 2 joints have now been placed this morning.
10:03an- 5 joints now placed and digging for MH E40 is next.
11:10am- grade is checked at MH E40. 2” low.
11:50am- MH E40 is now tied to line with a 12’ piece of pipe.
Line is lamped back to E39.
This picture is from MH E39 looking downstream to MH E38 today. I forgot to post it yesterday.
1:57pm- 1st joint placed upstream of E40 now.
3:34pm- 3rd joint upstream of E40 almost ready to go in for a total of 10 joints so far today.
4:29pm- joint 11 goes in.
5:05pm- high rock is encountered. Jack hammer will be put on for first thing in the morning.
Comments