Turkey Creek Ph 2 - Interceptor


6:58am- crew is back this morning to lay more pipe and set MH E41 today. 

7:32am- rock is encountered so Jack hammer is back on. 

8:30am- 2 joins are now placed this morning. 

9:42am- 4th in working on #5. 

10:42am- 5th joint is placed and MH E41 is getting graded out for setting. 

11:30am- MH E41 is now set with a 13’ piece of pipe tying it to the line. 

Line is also lamped by laser back to MH E40. 

1:45pm- alignment to MH E42 is complete and the 2nd joint out of E41 is getting gravel. 8 joints laid so far today. 

3:10pm- manholes are being unloaded here at site today. 

4:16pm- 12 joints of pipe laid so far now. 

5:05pm- crew will get joint 15 for today. 