6:58am- crew is back this morning to lay more pipe and set MH E41 today.
7:32am- rock is encountered so Jack hammer is back on.
8:30am- 2 joins are now placed this morning.
9:42am- 4th in working on #5.
10:42am- 5th joint is placed and MH E41 is getting graded out for setting.
11:30am- MH E41 is now set with a 13’ piece of pipe tying it to the line.
Line is also lamped by laser back to MH E40.
1:45pm- alignment to MH E42 is complete and the 2nd joint out of E41 is getting gravel. 8 joints laid so far today.
3:10pm- manholes are being unloaded here at site today.
4:16pm- 12 joints of pipe laid so far now.
5:05pm- crew will get joint 15 for today.