Turkey Creek Ph 2 - Interceptor
Once haul truck is back running, crew will continue with riprap and cleanup here today under bridge.
8:48am- truck is back running and dirt was hauled to low spot under bridge. Dirt to be spread out later today.
Crew is back to moving ground.
10:16am- creek is taking shape again.
11:28am- more riprap now going in on MH E6 side.
1:22pm- MH E6 is getting adjusted back down 2’ so that the surrounding ground can be graded to it.
2:14pm- barrel section now changed out.
2:53pm- wrapped and strapped!
3:51pm- Terry Snowden stops by site today. Still wants the right grass seed to be sowed.
4:21pm- riprap beginning at MH E11- E12 crossing. This will round out the day.