7:02am- crew will be moving riprap around near MH’s 18-24 this morning while waiting on rock to be delivered to the end of Carlton so that pipe laying can continue. Brush will also be getting pulled up and piled in roadway from MH’s 35-40 so that it can be burned.
9:55am- slow day so far…
10:43am- back to digging today.
11:28am- 1st joint placed and now digging out for MH E45.
12:56am- joint #2 goes in. A short 5’ section of pipe will tie into manhole.
2:15pm- MH E45 is set and line is lamped by laser back to MH E44.
3:33pm- 1st joint now laid upstream of MH E45.
4:10pm- joint 2 now out of MH E45 for a total of 4 full joints so far today.
4:42pm- 5th full joint for today going in. This will round out the day as crew will go downhill to load a bad manhole up and take it to the top.