Turkey Creek Ph 2 - Interceptor
7:12am- laser is set up and crew will begin at MH E43 today.
8:04am- 1st joint is getting placed now.
9:41am- 2nd joint getting gravel.
10:00am: Met Junior w/ Boyce at Buffalo Ridge Clubhouse Pump station to go over a couple items.
12:01pm- 4 joints have now been placed so far today.
1:30pm- 5th joint now placed.
2:33pm- joint #6 going in.
3:35pm- 7th joint now and placed.
5:02pm- crew has achieved 9 joints for today! They are now within 30’ of MH E44.