Turkey Creek Ph 2 - Interceptor
7:00am- crew will continue with testing of manholes and line today.
7:46am- airing up test balls in lines at MH E7 to continue with vacuum testing.
8:21am- tightening bolts on MH E7 ring as vacuum test failed.
9:03am- MH E7 now passes vacuum test after redoing ram-nek under ring and lid.
9:45am- E8 MH Passes vacuum test.
10:51am- MH E9 fails test due to Ram-Nek issue under ring. Crew will have to dig up and fix.
11:04am- MH E9 passes vacuum test after pushing down on ring and lid with excavator.
11:46am- MH E10 passes vacuum test.
1:44pm- ring is pulled from MH E11 after several attempts to get it to pass vacuum test. New ram-nek to be installed.
2:24pm- MH E11 now passes vacuum test.
3:06om- testing equipment is moved to MH E12 side now. Air compressor is broke so crew will fall back and continue with grouting for the rest of today.
4:30pm- MH E9 is now grouted. Flowline and pipes
4:57pm- crew is going to call it a day.