7:17am- Met with Scott Bailey this morning to go over the issues from previous phases.
Crew is setting up for a test on the line from E12 to E13 this morning.
8:32am- line now on test from E12-E13. Approximately 103 min test.
10:13am- Line passes air test from E12-E13.

11:28am- MH E12 is vacuum tested and does not pass. Air leaking at casting and manhole. Crew will fix and retest.
11:28am- MH E12 is vacuum tested and does not pass. Air leaking at casting and manhole. Crew will fix and retest.
11:41am- MH E12 now passes vacuum test.
1:55pm- line now on test from MH E14-E13. Approximately 104 min test.
3:39pm- Line passes air test from E14-E13.
4:04pm- MH E13 passes vacuum test.
4:57pm- MH E14 is getting vacuum tested now.
5:00pm- MH E14 passes vacuum test.