Turkey Creek Ph 2 - Interceptor
Crew will be placing riprap today as well as starting testing on line at E1 manhole.
7:45am- riprap going in between MH E18-19 now.
9:10am- testing to begin here shortly at E2-E1.
Water will need to be pumped first from line or crew will move up line to where there is no water in the pipe.
11:40am- testing finally begins at MH E6 to E5. On test for approximately 95 mins.
1:17pm- line passes.
3:31pm- line on test again from E6-E7 for approximately 59 minutes.
4:31pm- line passes.
4:58pm- no more line to be tested today. This will round out the week.