Turkey Creek Ph 2 - Interceptor


7:21am- crew will get MH E21 set up for a vacuum test first thing this morning. 

7:37am- MH E21 passes vacuum test. 

8:49am- MH E23 passes vacuum test. 

9:14am- line now on test from MH E24-E23. Approximately 101min test. 

9:30am-1:00pm- met with Brad (TCRSD), Scott (FlatCreek), Terry Snowden and Tom head to look at issues with Ph1 & Ph 2. Scott has a list of things he states will be taken care of. 

11:17am- line passes air test from MH E24-E23. 

2:17pm- line now on test from MH E24-E25. 
Approximately 87 min test. 

3:00pm- more grouting to continue now. 

3:40pm- MH E19 almost finished with grout. 

3:50pm- line passes air test from MH E24-E25. 

4:47pm- crew will move some equipment around to round out the day. A look at some cleanup on hill. 