Turkey Creek Ph 2 - Interceptor


6:57am- crew will be only grouting manholes today starting back at MH E1 this morning. Hydraulic cement will be unloaded here first. 

8:25am- crew now at E1 to begin grouting. 

8:42am- E1 upstream pipe now grouted. Flowline and pipe out was previously grouted on Ph 1. 
8:53am- now at E2. Crew will continue grouting and I will inspect rest of their work on Monday. I will be offsite rest of the day. 