Turkey Creek Ph 2 - Interceptor


7:14am- crew is back at MH E6 to continue with grouting. 

9:10am- after some debris was removed from MH E6 side crew jumped to grout E7. 

9:56am- cleaning more debris from lune at MH E6 again. 

11:54am- MH E6 now grouted. 

12:43pm- Survey is onsite staking Rittenhouse property lines. 



2:43pm- crew working on MH E8 now. 

4:14pm- crew now working at MH E10. 
4:46pm- MH E10 will round out the day. 