Turkey Creek Ph 2 - Interceptor


7:04am- 3more slope anchors to be poured today and maybe re testing to be done. Manholes for lune extension will begin to arrive on Wednesday. 

8:35am- the last anchor is now built as concrete has arrived. 



8:54am- the past 3 anchors are now completed for a total of 9 between E46 & E47 manholes. 

10:35am- raising MH E41 2’ by a barrel section due to it setting in a low spot. 



11:20am- equipment will be brought back to MH E24 area to begin testing again. Air compressor will need to arrive as well. 

2:06pm- with the air compressor finally getting jere, the crew has now vacuum tested E22 and it passes. 

2:43pm- MH E24 passes vacuum test. 

3:53pm- MH E25 passes vacuum test. 

4:40pm- MH E26 passes vacuum test. 